Here is the Weekly Road Work Report from the Texas Department of Transportation for  April 15-21.

Bowie County

US 259 – At Red River north of De Kalb, constructing new bridge.

US 259 – From US 82 to FM 44, adding shoulders.

FM 1297 – From FM 2878 to FM 559, widening highway.

Camp County

None

Cass County

None

Harrison County

I-20 Westbound – From SH 43 to Gregg County Line, repairing pavement. Various lane closures, expect delays.

FM 2625 – From SH 43 to 0.5 mile west, constructing mine haul road overpass.

US 59 – From SH 43 South to I-20 in Marshall, resurfacing highway

Marion County

None

Morris County

None

Panola County

SH 149 – At SH 315, constructing overpass and widening highway.

US 59 – At US 79 overpass, replacing bridge rails. Traffic reduced to one lane each direction.

SH 149 – From Rusk County Line to FM 124, resurfacing highway.

Titus County

US 271 – From end of freeway section of US 271 to 0.3 mile south of FM 3417, extending freeway lanes and constructing overpass at FM 3417.

US 271 – At Ripley Creek and Ripley Creek Relief, replacing bridges.

Upshur County

SH 155 – From south of Sabine River to US 80, replacing bridges and widening roadway.

SH 155 – From FM 1002 to US 259, upgrading guard rail.

 

 