Another busy week across the area as road crews and road construction continues. Be advised when traveling throughout the work week in the following locations.

Bowie County

SH 8 – At Sulphur River, replacing bridges.

US 59 – From FM 989 to FM 2148, resurfacing highway.

Cass County

FM 3129 – From US 59 to SH 77, resurfacing highway.

SH 11 – From Morris County Line to FM 130, upgrading guard rails.

SH 8 – At Sulphur River, replacing bridges.

Harrison County

SH 43 – at I-20 overpass, conducting preventative maintenance work on overpass.

Loop 281 – at I-20 overpass, conducting preventative maintenance work on overpass.

I-20 – at the Louisiana State Line, LaDOTD is conducting a bridge widening project just across the state line. Expect delays and watch for stopped traffic.

FM 9 – From FM 2625 to Panola County Line, resurfacing highway.

FM 451 – From 0.6 mile east of FM 31 to FM 9, resurfacing highway.

I-20 Frontage Road – From US 259 to Loop 281, repairing and resurfacing highway.

FM 449– From Gregg County Line to FM 450, seal coating highway.

Morris County

US 259 – From FM 250 to FM 557, upgrading guard rails, repairing pavement and resurfacing highway.

SH 49 – From Titus County Line to FM 144, repairing and resurfacing Highway.

FM 3421 – From FM 250 to US 259, seal coating highway.

Panola County

SH 149 – At SH 315, constructing overpass and widening highway.

US 59 – From FM 2792 to Harrison County Line, upgrading guard rails, repairing pavement and resurfacing highway.

US 79 – From US 59 to Sabine River, resurfacing highway.

Titus County

US 271 – At Ripley Creek and Ripley Creek Relief, replacing bridges.

FM 899 – At Dragoo Creek, replacing bridge. Highway closed to through-traffic.

SH 49 – From FM 1735 to Morris County Line, repairing and resurfacing highway.

Upshur County

US 259 – From FM 557 to SH 155, repairing and resurfacing highway.

SH 155 – From US 259 to 5 miles south of US 259, resurfacing highway.

FM 1002 – From SH 155 to SH 154, seal coating highway.