Traveling to and from home to work this week be advised of more road work and construction that continues in our region. Slow down in work-related areas and be on the lookout for road crews.
Bowie County
SH 8 – At Sulphur River, replacing bridges.
US 59 – At Akin Creek, replacing guard rail.
Cass County
SH 8 – At Sulphur River, replacing bridges.
Harrison County
I-20 – At Potters Creek, conducting preventative maintenance work on bridges.
SH 43 – From Loop 390 to Haggerty Creek, repairing and resurfacing highway.
US 59 – From Marion County Line to Woodlawn Oaks Road, installing median barrier.
Marion County
US 59 – From FM 2208 to Harrison County Line, installing median barrier.
Morris County
SH 49 – From Titus County Line to FM 144, repairing and resurfacing highway.
Panola County
SH 149 – At SH 315, constructing overpass and widening highway.
US 59 – at SH 149 interchange, concrete pavement replacement. East side entrance and exit ramps closed. Detours in place.
US 79 – From FM 31 to Louisiana State Line, resurfacing highway.
Titus County
SH 49 – From FM 1735 to Morris County Line, repairing and resurfacing highway.